Bostwick Road Environmental Assessment

Background

Bostwick Road is a major street that can connect future development in southwest London to the rest of the city.

This Environmental Assessment was initiated to consider realigning Bostwick Road west of Wharncliffe Road to increase capacity, accessibility and better serve all areas of the city – changes that were previously recommended by the City’s Transportation Master Plan and the Southwest Area Plan.

The study also reviewed the possibility of extending Bradley Avenue to Pack Road as part of any potential construction.

The project team considered alternative ways to construct these changes as part of the Environmental Assessment, and ultimately recommended the Bostwick Road realignment and Bradley Avenue extension through the Environmental Study Report.

Current status

This Environmental Assessment is now complete. In April 2019, City Council approved the Bostwick Road realignment along with the Bradley Avenue extension. Both streets will be four lanes wide. Construction of Bostwick Road from Pack to Wharncliffe is expected to happen in 2026.

Study area

Image
The study area is Bostwick Road from Pack Road to Wharncliffe Road (extension of Exeter Road). The Bradley Avenue extension runs from Bostwick Road to Wonderland Road South. For more information, please contact Michelle Morris, Transportation Design Engineer, at 519 661-2489 ext. 5806 or mmorris@london.ca

 

Project Timeline

2016: Start of the Environmental Assessment

The City sent out a notice of commencement to residents, business owners and interested stakeholders to notify them of the Environmental Assessment's start.

October 2016: First Public Information Centre

A Public Information Centre was held in October 2016, to collect public feedback on the potential realignment of Bostwick Road. 

June 2017: Second Public Information Centre

A Public Information Centre was scheduled for June 2017 at Lambeth Community Centre. The team provided all interested parties with an update on the project and listened to feedback that was critical to shaping the recommendations provided by the Environmental Study Report.

April 2019: Environmental Study Report released

The Environmental Assessment is now complete, and Council approved the plan in 2019.

Last modified:Thursday, April 11, 2024